Construction Project – Phase 2 (Diamond T Garage)

Diamond T Garage

November 12, 2021.  The Diamond T is back in it’s forever home. Looks Awesome!

November 1, 2021 – Completed Diamond T Garage.  Just waiting to get the “T” back from getting the breaks fixed.

October 22, 2021 – Getting the floor done in the Diamond T Garage.

October 7, 2021 – The decision was made last night to apoxy the floor of the Diamond T Garage (similar to the truck room floor) before the Diamond T comes back from repair!  Thank you Dylan for offering to complete this work!  This weekend (October 9-10), the work will be started!  PLEASE DO NOT ENTER THE GARAGE… they will be cleaning the floor and prepping to apoxy it!

September 1, 2021

Diamond T Garage construction is complete, now we just have to wait to get the Diamond T back from repair of breaks, items need to be put up onto the walls and floor needs to be cleaned.

August 29, 2021.  Glass is in, mirrors arrived and some were broken during delivery.

August 23, 2021.  Just waiting on mirror and glass that was broken in delivery.  Then this phase will be completed.